Facade Retention Scheme on Brook Street

Bricks retained for reuse in scheme

Portland Stone retained for facade rebuild

Constuction site

Constuction site

Constuction site
Construction Timeline
July 2018 - May 2020
Public consultation on the proposal
2020
Planning application submitted to Westminster City Council
2020
Statutory consultation and continued engagement with the local community
November 2023
Demolition and construction works start
2024
Works start on South Molton Street properties
2025
Main buildings works commence on North and South buildings
2025
Works complete on South Molton Street properties
2026
Public realm works commence
2027
The South Molton Triangle is complete and open to everyone